Thursday 5 June 2008

Day 57 - Windows and Roofing Felt

Progress has been slower than expected this week due to bad weather. You can see from the pictures just how wet its been.

Despite this though there has been a lot going on. The sand and cement for the brick layers has been delivered, the roofers have made a start on the felt and batton work on the roof and, best of all, the first of the sash windows have been delivered!

A groundworks crew also arrived to drop the curb on the entrance to Number 49 which will allow the new owner of the bungalow to put in their own driveway and allow us to complete the fence to ours.

The roofers are back for the rest of the week to complete the felt work and Ben and his brick layer team will be working hard to get started despite the wet ground conditions.