Tuesday 24 June 2008

Day 67 - Roof complete

The work to the roof is complete now and the brick work is moving on a pace.

    
Posted by Picasa

Sunday 22 June 2008

Day 66 - Getting there

The brick work is almost up to the first floor now, with the first stone sills in a looking great. The roof is almost finished as well, with only a few tiles and ridge tiles missing.

    
Posted by Picasa

Tuesday 17 June 2008

Day 63 - Almost up to DPC

The brick work is continuing slowly but surely. We should be up to DPC after one more day.

    
Posted by Picasa

Thursday 12 June 2008

Day 61 - Soldier Course

The below DPC brick work continued today, with most of the work both on the roof and the bricks going on at the back of the house. You can see the nice soldier course detail below the back door and the first of the complete sections of slate work - scaffold climbing required!

    
Posted by Picasa

Wednesday 11 June 2008

Day 60 - Bricks & Windmills

The brick work has begun today and the brickies have started to define the corners of the below DPC courses. The slates have also arrived and are going up on the roof - all at the back of the house though so I can't get a picture from the ground. I'll have to climb the scaffold for you later in the week and get a shot.

We went for a walk on the Fen last night too and, although all of the wildlife was in hiding, I got some good pictures of the Wicken windmill on the way back.

    
Posted by Picasa

Friday 6 June 2008

Day 58 - Ground Floor Windows

The ground floor windows are now in and the roofing effort continues.

I've also had confirmation that slates will be arriving on Monday/Tuesday next week!

   
Posted by Picasa

Thursday 5 June 2008

Day 57 - Windows and Roofing Felt

Progress has been slower than expected this week due to bad weather. You can see from the pictures just how wet its been.

Despite this though there has been a lot going on. The sand and cement for the brick layers has been delivered, the roofers have made a start on the felt and batton work on the roof and, best of all, the first of the sash windows have been delivered!

A groundworks crew also arrived to drop the curb on the entrance to Number 49 which will allow the new owner of the bungalow to put in their own driveway and allow us to complete the fence to ours.

The roofers are back for the rest of the week to complete the felt work and Ben and his brick layer team will be working hard to get started despite the wet ground conditions.

         

Sunday 1 June 2008

Day 55 - Bricks!

The first delivery of bricks is now onsite, albeit blocking access to everything else!

The roofers have begun to get everything organised, and the stone sills arrived on Wednesday - I had to offload them all by hand. Luckily they only weigh 1.3 tonnes...

I'm going to try to recover some of the time lost from the ground works by having the roofers and bricklayers work on site together. It should be all systems go next week.

    
Posted by Picasa