We have a floor!
The screeders have done a great job and the new floor looks first class. I can only take shots from the doorway at the moment as we can't walk on it yet but after Christmas it should be solid enough for us to march on.
They did however make a bit of a mess - I have them coming back tomorrow to clean up after themselves!
A diary of my attempts to build a new house in Wicken, Cambridgeshire. How hard can it be?
Saturday 13 December 2008
Wednesday 10 December 2008
Day 106 - Ready to Screed
Monday 8 December 2008
Day 104 - We're Back!
The banks have been useless but with a lot of hard work and a good dose of luck we're finally back in business and work is underway once again.
The ground works have been completed on the exterior; the drains are in for both foul and surface water with a pump house half way up the drive.
The plumbing is underway with the underfloor heating system arriving on site on Tuesday last week and the ground floor insulation and screed are being laid today and Thursday.
Andy and I completed the guttering as well last Tuesday, hooking up the down pipes to the underground pipework that links into the rainwater harvester.
It's all go!
The ground works have been completed on the exterior; the drains are in for both foul and surface water with a pump house half way up the drive.
The plumbing is underway with the underfloor heating system arriving on site on Tuesday last week and the ground floor insulation and screed are being laid today and Thursday.