Friday 24 October 2008
Thursday 16 October 2008
Day 94 - Progress at last
We are STILL waiting on the bank (a new one now) to okay the final cash - talk about picking the wrong year to build a house - but work has resumed on site nonetheless.
The ground workers are back to hook up the drains and landscape the plot. Their work will include hardcoring all of the paved surfaces, installing a sewer pump and pipework, hooking up the guttering to the rainwater harvester and levelling and gravelling the drive.
The ground workers are back to hook up the drains and landscape the plot. Their work will include hardcoring all of the paved surfaces, installing a sewer pump and pipework, hooking up the guttering to the rainwater harvester and levelling and gravelling the drive.